Description of the Works
Removal of Journals and bookcases to make way for an additional 88 student quiet study spaces including new carpet, new furniture with power and additional WiFi cover to the area.
Timescale
Works commence on Monday 3rd August and will be completed on Thursday 24th September 2026.
No works will take place during Open Days - 18th & 19th September 2026
Contractors working hours are 07:00-16:30 daily
How can I get more information and help?
The Estates and Facilities Management team member looking after the task is detailed below and can be contacted about any difficulties experienced because of these works.
Name and Job Title: Tim Oakey - Project Manager
Mobile: 07966 828356
Email: t.s.oakey@lboro.ac.uk.